Decision 83-H
https://had.aer.ca/link/decision2272
- Applicant
- Alberta Power Limited
- Application Number
- 830799
- Title
- Decision on application by Alberta Power Ltd., 1983 (to amend approvals to defer unit commissioning dates - Sheerness and Genesee power plants); electric generation expansion 1985-1990 Sheerness and Genesee power plants
- Date
- 1983
- Title
- Decision on application by Alberta Power Ltd., 1983 (to amend approvals to defer unit commissioning dates - Sheerness and Genesee power plants); electric generation expansion 1985-1990 Sheerness and Genesee power plants
- Date
- 1983
- Applicant
- Alberta Power Limited
- Application Number
- 830799
- Hearing Panel
- Goodman CJ
- Strom NA
- Mink FJ
- Hearing Type
- Board
- Utilities
- Category
- Electric power
- Descriptors
- Electric power project
- Genesee power plant
- Sheerness power plant
- Benefit cost analysis
- Capacity
- Electric power demand
- Electric power supply
- Forecasting
- NTS 72M
- NTS 82P
- NTS 83G
- Planning
- Power system interconnection
- Revision
- Legal References
- Energy Resources Conservation Act S42
- Hydro and Electric Energy Act S9
- Notes
- Decision D83-H on application No. 830799 by Alberta Power requesting amendments to the Sheerness and Genesee power plant approvals to defer the unit commissioning dates of Sheerness generating units 1 and 2 and Genesee generating units 2 and 1; errata dated Jan. 10, 1984 included; Board hearing 1983-09-28/29; see related reports 79-AA (& addendum), 80-B and 82-C