13 records – page 1 of 1.

Decision 79-AA

https://had.aer.ca/link/decision2391
Applicant
Alberta. Dept. of the Environment
Alberta Power Limited
Forestburg Collieries Limited
Manalta Coal Ltd.
Edmonton Power
Application Number
9759
770364
780041
780024
Title
Decision on application by Alberta Power Ltd., Forestburg Collieries Limited and Manalta Coal Ltd., 1979 (Sheerness mine and the construction and operation of proposed Sheerness thermal power plant) and on application by Edmonton Power Ltd., 1979 (Genesee thermal power plant and Genesee mine)
Date
1979
Title
Decision on application by Alberta Power Ltd., Forestburg Collieries Limited and Manalta Coal Ltd., 1979 (Sheerness mine and the construction and operation of proposed Sheerness thermal power plant) and on application by Edmonton Power Ltd., 1979 (Genesee thermal power plant and Genesee mine)
Date
1979
Applicant
Alberta. Dept. of the Environment
Alberta Power Limited
Forestburg Collieries Limited
Manalta Coal Ltd.
Edmonton Power
Application Number
9759
770364
780041
780024
Hearing Panel
Berkowitz N
DeSorcy GJ
Goodman CJ
Thiessen HW
Hearing Type
Board
Utilities
Category
Coal
Descriptors
Coal mine
Coal project
Electric power project
Genesee mine
Genesee power plant
Roselyn mine
Sheerness mine
Sheerness power plant
Thermal power plant
Alberta
Benefit cost analysis
Capacity
Coal - fuel
Comparison
Cooling system
Cost analysis
Electric power demand
Environmental impact
Locating
Mine design
NTS 72M
NTS 83G
Planning
Plant design
Socio-economic effect
Legal References
Coal Conservation Act S10
Coal Conservation Act S21
Hydro and Electric Energy Act S7
Hydro and Electric Energy Act S14
Notes
ERCB Report 79-AA (with separate addendum) on application No. 9759 by Alberta Power for plant near Sheerness and connection to its electric system, application No. 770364 by Forestburg to develop a mine site near Sheerness to supply proposed Power Plant, application No, 780041 by Manalta to extend Roselyn mine (Mine No. 443) at Sheerness to supply part of coal for proposed Sheerness power plant (Sheerness in TP.24-31, R.11-16, W4M) and on application No. 780024 by Edmonton Power thermal power plant at Genesee and mine site at Genesee to supply coal to fuel the plant (TP.48-51, R.1-4, W5M); See also ERCB Report 82-C for decision on later application by Edmonton Power to advance the commissioning dates for Genesee plant; Board hearing on Sheerness 1978-05-16/17/18/19; Board hearing on Genesee 1978-07-25/26/27/28 & 1978-08-02/03/04
Interveners
Alberta Power Limited
McDermid, N
Provost, K
Frey, JR
Leahy, DM
Griffing, TC
Kolisnyk, Z
Manalta Coal Ltd.
Forsyth, GR
McKinnon, S
Chapel, GD
Shaneman, M
Portigal, L
Eeglon, T
Morgan, JR
Forestburg Collieries Limited
Parr, R
Morris, JE
Engler, RF
Robbins, GH
Haddock, JK
Bowman, PM
McAllister, RE
Electric Utilities Planning Council (EUPC)
Ferguson, T
Chorel, MJ
Reed, WA
Beckett, WJ
Fleury, D
Shinyei, F
Hosie, W
Desarkar, A
Calgary Power Ltd.
Sabey, DO
Kay, HM
Fraser, WL
Barry, EJ
Scheaffer, HG
Crowe, TW
Friend, A
Williams, MM
City of Edmonton
Smith, P
Kyte, EF
Department of Municipal Affairs Special Areas Board
Duff, AR
Unifarm Region Eleven
Gordon, H
Williams, CK
Price, RH
Anderson, D
Brown, V
Cambell, C
Hutton, LC
Bull Pound Breeders' Co-operative Ltd.
Lenfesty, Ma
McEwen, MO
Hartzler, C
T.G. Cattle Company Limited
Gateman, J
Cattle, TG
Department of Environment staff
Defir, J
Harrington, DG
Lupul, S
Deagle, C
Edmonton Power
Patterson, M
Pettican, A
Sadesky, A
Keller, A
Warren, K
Pelletier, D
Prostebby, J
Clark, D
De, M
Visman, J
Gilchrist, G
Majury, A
Stutz, C
Croft, B
Lamb, A
Gill, D
Stewart, R
MacDougall, T
Dusel, F
Brocke, L
Reeves, B
Warburg and District Chamber of Commerce
Siega, L
Village of Warburg
Zotzman, E
Town of Drayton Valley
Welsh, MC
McKay, A
McKay, R
Osbak, E
Save-Tomorrow-Oppose Pollution (S.T.O.P.)
Poulin, J
Paschen, J
Royen, L
McGaffey, P
Wighton, D
Town of Hanna
Dookie, SS
Sierra Club of Alberta
Kariel, P
Genesee Agricultural Protection Society (G.A.P.S.)
Skermer, R
Liba, Z
Koebernick, W
Mertz, W
Koebernick, E
Liba, L
Group of Concerned Genesee and Area Citizens
Lorincz, S
Fritz, C
Lawrence, KC
Unifarm
Falconberg, H
Bell, S
Smith, R
County of Leduc
Warburg Coal Company
Christian Farmers Federation
Vanderschaaf, Mr
Less detail

Decision 80-B

https://had.aer.ca/link/decision2327
Applicant
Calgary Power Ltd.
Application Number
790693
Title
Decision on application by Calgary Power Ltd., 1980 Keephills Power Plant expansion
Date
1980
Title
Decision on application by Calgary Power Ltd., 1980 Keephills Power Plant expansion
Date
1980
Applicant
Calgary Power Ltd.
Application Number
790693
Hearing Panel
Berkowitz N
Goodman CJ
Thiessen HW
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power project
Genesee power plant
Keephills power project
Thermal power plant
Benefit cost analysis
Capacity
Coal - fuel
Comparison
Electric power demand
Electric power supply
Expansion
NTS 83G
Legal References
Hydro and Electric Energy Act S7
Hydro and Electric Energy Act S14
Notes
ERCB Report 80-B on application No. 790693 for construction and operation of two additional generating units (Unit 3 and 4) at Keephills Power Plant (TP.51-52, R.3-4, W5M); Board hearing 1980-01-29/30/31 & 1980-02-01 See also ERCB Report 82-C for decision on later application by TransAlta for Keephills expansion
Interveners
Calgary Power Ltd.
Sabey, DO
Kay, M
Fraser, WL
Chorel, M
Roxburgh, P
Railton, J
Candy, R
Gleghorn, D
Behie, S
DeSanto, JE
Alberta Power Limited
McDermid, N
Brascan Resources Limited
Stein, J
Committee on Keephills Environment (COKE)
Chow, M
Swist, RC
White, E
MacDougall, M
County of Parkland
McCullough, M
Miller, LN
Breckenridge, C
Edmonton Power
Patterson, MH
Kyte, E
Pettican, A
Sadesky, A
Warren, K
Majury, R
Electric Utility Planning Council (EUPC)
Cairns, RM
Hanslip, G
DeSarkar, A
Lake, G
Ewashko, JE
Fording Coal Limited
Hope-Ross, WJ
Rushton, HG
Genesee Agriculture Protection Society
Koebernick, W
Liba, L
Broadbent, H
Mertz, W
Genesee and Area Concerned Citizens Group
Lorincz, S
Lawrence, KW
PanCanadian Petroleum Limited
Little, GE
Duthie, RH
Porter, K
Porter Ranches Ltd.
Price, E
Porter, C
Quigg, A
Quigg, R
Swisht, RC
Warburg Coal Company
Siega, L
Department of Environment (Alberta Environment)
Lupul, S
Lang, D
Less detail

Decision 82-C

https://had.aer.ca/link/decision2312
Applicant
TransAlta Utilities Corporation
Edmonton Power
Application Number
810222
810683
Title
Decision on application by TransAlta Utilities Corporation, 1982 (Keephills decision on application by Edmonton Power, 1982 (Genesee units 1 and 2 com generation expansion 1985-1987 Keephills and Genesee power plants
Date
1982
Title
Decision on application by TransAlta Utilities Corporation, 1982 (Keephills decision on application by Edmonton Power, 1982 (Genesee units 1 and 2 com generation expansion 1985-1987 Keephills and Genesee power plants
Date
1982
Applicant
TransAlta Utilities Corporation
Edmonton Power
Application Number
810222
810683
Hearing Panel
Berkowitz N
Goodman CJ
Warne GA
Mink FJ
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power demand
Electric power project
Genesee power plant
Keephills power project
Thermal power plant
Alberta
Benefit cost analysis
Capacity
Coal - fuel
Cooling
Cost analysis
Economic analysis
Economic forecasting
Electric power supply
Energy development
Environmental impact
Expansion
Forecasting
Land reclamation
NTS 82O
NTS 83G
Planning
Reliability
Legal References
Hydro and Electric Energy Act S9
Notes
ERCB Report 82-C on application No. 810222 by TransAlta to construct Keephills unit 3 and 4 and on application No. 810683 by Edmonton Power to advance commissioning dates for Genesee units 1 and 2; Board hearing on Keephills 1981-06-24/25; Board hearing on Genesee 1981-11-25; See also related reports ERCB 79-AA (Genesee Power Plant) and ERCB 80-B (Keephills Power Plant expansion)
Interveners
TransAlta Utilities Corporation (Formerly Calgary Power Ltd.)
Sabey, DO
Kay, M
Fraser, WL
Lyons, GD
Crowe, T
Chorel, M
Railton, J
Robinson, J
Alberta Power Limited
Beames, J
Frey, JR
Jones, RG
McDermid, N
City of Edmonton (Edmonton Power)
Sherk, M
Kyte, E
Pelletier, D
Pettican, RA
Warren, K
Shinyei, F
DeSarkar, A
Electric Utility Planning Council (EUPC)
Ferguson, TH
Gardiner, P
Paicu, G
Gunn, J
The County of Parkland No. 31
Twach, T
Breckenridge, C
Committee on Keephills Environment
Ewashko, J
Department of Environment
Shewchuk, P
Fringe Environment Area Residents
Staszenski, B
Friends of the River
Smith, JH
Less detail

Decision 83-07

https://had.aer.ca/link/decision2389
Applicant
City of Edmonton
Application Number
810932
Title
Decision on application by City of Edmonton, 1983 (500 KV transmission lines, Genesee area)
Date
1983
Title
Decision on application by City of Edmonton, 1983 (500 KV transmission lines, Genesee area)
Date
1983
Applicant
City of Edmonton
Application Number
810932
Hearing Panel
DeSorcy GJ
Hearing Type
Utilities
Category
Transmission line
Descriptors
Electric substation
Genesee power plant
High voltage
Transmission line
Environmental impact
Land value
NTS 83G
Reliability
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S17
Notes
Decision D83-7 on application No. 810932 for substation and switchyard at Genesee power plant and two transmission lines to connect switchyard to TransAlta Utilities 500-KV lines CP 1203L and CP 1209L; Decision adopts recommendations in Examiners report E83-11 which is appended to Decision
Interveners
Litzenberger, E.R.
TransAlta Utilities Corporation
Comeau, J.
Less detail

Decision 83-11

https://had.aer.ca/link/decision1194
Applicant
City of Edmonton
Application Number
810932
Title
Examiners report on application by City of Edmonton, 1983 (500-KV transmission lines Genesee area)
Date
1983
Title
Examiners report on application by City of Edmonton, 1983 (500-KV transmission lines Genesee area)
Date
1983
Applicant
City of Edmonton
Application Number
810932
Hearing Panel
Goodman CJ
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Genesee power plant
High voltage
Transmission line
Environmental impact
Land value
NTS 83G
Reliability
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S17
Notes
ERCB Examiners report E83-11 on application No. 810932 for permits and licences to construct and operate a switchyard at Edmonton Power's Genesee power plant and two single circuit steel tower transmission lines to connect the switchyard to TransAlta Utilities existing 500-KV transmission line 1203L-1209L (TP.50-51, R.2-3 W5M); see also addendum to this published as Examiners report E83-14; see also Board Decision D83-7 which is Board Decision adopting Examiners report
Interveners
Litzenberger, E.R.
TransAlta Utilities Corporation
Comeau, J.
Less detail

Decision 83-14

https://had.aer.ca/link/decision1191
Applicant
City of Edmonton
Application Number
810932
830684
Title
Examiners report on application by the City of Edmonton, 1983 (500- KV transmission lines Genesee area)
Date
1983
Title
Examiners report on application by the City of Edmonton, 1983 (500- KV transmission lines Genesee area)
Date
1983
Applicant
City of Edmonton
Application Number
810932
830684
Hearing Type
Utilities
Category
Transmission line
Descriptors
Electric substation
Genesee power plant
High voltage
Transmission line
Design criteria
NTS 83G
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Notes
ERCB Examiners report E83-14 on application No. 810932 and No. 830684 (addendum to Examiners report E83-11) for permit, licence, and Order to construct, interconnect and operate Edmonton Power's proposed 500-KV substation and switchboard
Less detail

Decision 83-H

https://had.aer.ca/link/decision2272
Applicant
Alberta Power Limited
Application Number
830799
Title
Decision on application by Alberta Power Ltd., 1983 (to amend approvals to defer unit commissioning dates - Sheerness and Genesee power plants); electric generation expansion 1985-1990 Sheerness and Genesee power plants
Date
1983
Title
Decision on application by Alberta Power Ltd., 1983 (to amend approvals to defer unit commissioning dates - Sheerness and Genesee power plants); electric generation expansion 1985-1990 Sheerness and Genesee power plants
Date
1983
Applicant
Alberta Power Limited
Application Number
830799
Hearing Panel
Goodman CJ
Strom NA
Mink FJ
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power project
Genesee power plant
Sheerness power plant
Benefit cost analysis
Capacity
Electric power demand
Electric power supply
Forecasting
NTS 72M
NTS 82P
NTS 83G
Planning
Power system interconnection
Revision
Legal References
Energy Resources Conservation Act S42
Hydro and Electric Energy Act S9
Notes
Decision D83-H on application No. 830799 by Alberta Power requesting amendments to the Sheerness and Genesee power plant approvals to defer the unit commissioning dates of Sheerness generating units 1 and 2 and Genesee generating units 2 and 1; errata dated Jan. 10, 1984 included; Board hearing 1983-09-28/29; see related reports 79-AA (& addendum), 80-B and 82-C
Less detail

Decision 85-21

https://had.aer.ca/link/decision1274
Applicant
Alberta Power Limited
City of Edmonton
Transalta Utilities Corporation
Application Number
840837
Title
Decision on proceeding to amend approval HE 8312 held by Alberta Power Ltd. electric generation expansion 1986-1991 Sheerness and Genesee power plants
Date
1985
Title
Decision on proceeding to amend approval HE 8312 held by Alberta Power Ltd. electric generation expansion 1986-1991 Sheerness and Genesee power plants
Date
1985
Applicant
Alberta Power Limited
City of Edmonton
Transalta Utilities Corporation
Application Number
840837
Hearing Panel
Millard V
Goodman CJ
Mink FJ
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power generation
Electric power project
Genesee power plant
Sheerness power plant
Capacity
Coal - fuel
Cost analysis
Electric power demand
Expansion
Forecasting
Planning
Power system interconnection
Socio-economic effect
Notes
ERCB Decision D85-21 on proceeding No. 840837 to review commissioning dates of the Sheerness and Genessee generating units in the 1986-1991 period in light of events which occurred after issuance of Decision D83-H; Board Hearing 1985-01-22/23/24/25/30
Interveners
Electric Utility Planning Council (EUPC)
McAvity, EO
Hanslip, G
Gunn, J
Taylor, W
Valiant, R
Alberta Power Limited
Major, JC
Provost, K
Frey, JR
Lake, G
TransAlta Utilities Corporation
Patterson, MH
Hopkins, WJ
Fraser, WL
Crowe, T
The City of Edmonton (Edmonton Power)
Beames, JW
Sherk, M
Kyte, EF
Pettican, A
Wright, R
Wright Mansell Research Ltd.
The City of Calgary
Goss, RF
Larder, DA
The City of Lethbridge
Martin, E
Industrial Power Consumers Association of Alberta (IPCAA)
Curtis, R
Clark, BW
Fording Coal Limited
Smith, JR
Manalta Coal Limited
Holgate, DA
Portigal, L
Decker, J
Shaneman, R
Luscar Limited
MacDonald, M
Smith, D
Haddock, K
Electrical Contractors Association of Alberta (ECAA)
Soucy, GA
Energy Chemical Workers Union
Nielsen, R
Coe, E
Southern Alberta Building and Construction Trades (Southern Alberta)
Pittman, PRJ
Briegel, J
Alberta and N.W.T. (Distirct of Mackenzie) Building and Construction Trades Council
Garby, R
INTEG - Intercontinental Engineering Ltd.
Smith, MJ
Cana Construction Co. Ltd.
Dunlop, JD
The County of Leduc No. 25
Walter, EJ
Pinkowski, K
The Town of Hanna and District
McLarty, AL
Dookie, S
Grover, A
The Town of Calmar
McCartney, G
The Village of Warburg
Haggerty, D
The Village of Thorsby
Bacsik, L
Senio, B
The Village of Breton
Hilker, JD
Edmonton Economic Development Authority
Bleiken, AG
Battle River Regional Planning Commission
Scerbak, G
Fenwick, PD
Alberta Wind Power Associates
Otis, J
Less detail

Decision 91-12

https://had.aer.ca/link/decision31
Applicant
Edmonton Power
City of Edmonton
Application Number
910336
Title
Decision 91-12 : City of Edmonton (Edmonton Power) : Application for a review of commissioning date of Genesee unit No. 1
Date
1991
Title
Decision 91-12 : City of Edmonton (Edmonton Power) : Application for a review of commissioning date of Genesee unit No. 1
Date
1991
Applicant
Edmonton Power
City of Edmonton
Application Number
910336
Hearing Panel
Prince JP
Mink FJ
Evans RG`
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power project
Genesee power plant
Benefit cost analysis
Capacity
Electric power demand
Electric power supply
Decision D1985-21
Decision D1983-H
Expansion
Forecasting
Planning
Power system interconnection
Notes
ERCB Decision D91-12 on application No. 910336 by Edmonton Power to amend approval No. HE8505 to delete 1991 as the commissioning date and allow construction of Genesee Unit No. 1 to continue; Hearing held 1991-08-15/16
Interveners
The City of Edmonton (Edmonton Power)
Pettican, A
Shinyei, F
Topping, D
Tadman, D
TransAlta Utilities Corporation
Dalgleish, T
Tapics, J
Way, D
Alberta Power Limited
Romanow, D
Frey, R
Baer, R
Walker, J
The City of Calgary
Short, D
Industrial Power Consumers Association of Alberta (IPCAA)
McLarty, A
Fording Coal Limited
McIntyre, P
Northern Alberta Building Trades Council and Provincial Building Trades Council
Hall, M
County of Leduc
Sjolie, B
Western Oldman Water Users Association
Arsene, W
Energy Consulting Inc.
Town of Stettler
Jackson, A
Alberta Cogeneration Council
Logan, K
Whitford, T
The International Brotherhood of Electrical Workers (IBEW)
Turner, D
Northwest Territories Building and Construction Trades Council
Blakely, R
Less detail

Decision 2001-111

https://had.aer.ca/link/decision3490
Applicant
Epcor Generation Inc.
Epcor Power Development Corpoaration
Application Number
2001173
Title
Decision 2001-111: EPCOR Generation Inc. and EPCOR Power Development Corporation expansion of Genesee power plant
Date
2001
Title
Decision 2001-111: EPCOR Generation Inc. and EPCOR Power Development Corporation expansion of Genesee power plant
Date
2001
Applicant
Epcor Generation Inc.
Epcor Power Development Corpoaration
Application Number
2001173
Hearing Panel
McCrank MN
Lock RG
Miller GJ
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Electric power generation
Genesee Power Plant
Coal - fuel
Thermal Power Plant
Leduc area
NTS 83G
Decision D2001-33
Decision D2001-101
Environmental impact
Safety
Air pollution
Fisheries
Water pollution
Wildlife
Noise (sound)
Health
Human factor
Socio-economic effect
Cooling system
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S2
Energy Resources Conservation Act S2
Notes
EUB Decision 2001-111 on application no. 2001173 by EPCOR Generation Inc. and EPCOR Power Development Corporation to construct a 490-megawatt expansion to its existing coal-fired Genesee power plant at Rge 25-50-3 W5M
Interveners
Alberta Environment
Canadian Environmental Assessment Agency
Capital Health Authority
Clean Energy Coalition
Department of Fisheries and Oceans
ENMAX Energy Corporation
ENMAX Power Corporation
Enron Canada Corporation
Environment Canada
ESBI Alberta Ltd.
Fording Coal Limited
Hebner Group
Kruger Group (for the local area residents of Genesee)
Mewassin Community Action Group
Paul First Nation
TransAlta Utilities Corporation
TransCanada Energy Limited
Anderson AM
Bernette Ho L
Bird T
Bjorge R
Blackall P
Bodnarek R
Bradford J
Buchwald V
Bull A
Buss K
Cheng L
Chesterman D
Cook S
Cusano LA
Dobko R
Donahue W
Fairbairn M
Forster C
Forster L
Gagner E
Gaspe D
Good Striker D
Griffiths M
Hannaford DJ
Hebner B
Hebner D
Hemstock RN
Hnytka F
Huber HR
Kellerhals M
Kruger D
Lakeman B
Lawrence L
Lawrence S
Legge A
Lloyd D
MacDonald B
Mackenzie A
Mak A
Marr-Laing T
McDonald K
Paul D
Phillips L
Rain O
Rain P
Rain R
Ross G
Sawatsky N
Secord RC
Shores W
Stepaniuk DW
Stubbings
Tyrell H
Valupadas P
Vincent M
Wallace RB
Yanor-McRae R
Approval
Approved
Conditions
The Board expects that EPCOR will adhere to all commitments it made during the consultation process, in the application, and at the hearing on such matters as mitigation, monitoring, and bilateral agreements.
Location
##-25-050-03W5
Less detail

Decision Memorandum of Decision 1984-09-17

https://had.aer.ca/link/decision129
Applicant
Energy Resources Conservation Board
Application Number
840837
Title
Memorandum of Decision on Board initiated proceeding to review the commissioning dates of the Genesee and Sheerness generating units, 1984
Date
1984
Title
Memorandum of Decision on Board initiated proceeding to review the commissioning dates of the Genesee and Sheerness generating units, 1984
Date
1984
Applicant
Energy Resources Conservation Board
Application Number
840837
Hearing Panel
Millard, V
Hearing Type
Prehearing
Utilities
Category
Electric power
Descriptors
Electric power generation
Electric power project
Genesee power plant
Sheerness power plant
Capacity
Coal - fuel
Cost analysis
Electric power demand
Expansion
Forecasting
Planning
Power system interconnection
Socio-economic effect
Notes
Memorandum of Decision on proceeding No. 840837 to hear comments and views for the need for a public hearing to determine the currently approved commissioning dates for the Genesee and Sheerness generating units should be changed, the timing and place of such a hearing, the information required and terms of reference
Interveners
Alberta Power Limited
Major, JC
Provost, K
Frey, D
The City of Edmonton (Edmonton Power)
McDermid, QC
Kyte, EF
Pettican, A
TransAlta Utilities Corporation
Patterson, MH
Hopkins, WG
Fraser, WL
Chorel, MJ
Crowe, TW
The City of Calgary
Goss, RF
Steven, WG
Chymko, NJ
Kell, BF
Arsene, W
Konduc, G
Babcook, A
Mallon, DP
Fording Coal Limited
Smith, JR
Shyluk, DJ
The Industrial Power Consumers Association of Alberta
McDermott, D
Garritsen, H
Alberta Union of Rural Electrification Associations (AUREA)
Foster, JL
McGhan, A
Less detail

Decision Memorandum of Decision 1991-06-05

https://had.aer.ca/link/decision53
Applicant
Edmonton Power
Application Number
910336
Title
Memorandum of Decision on application by Edmonton Power, 1991 (Commissioning Schedule of Genesee Unit No.1)
Date
1991
Title
Memorandum of Decision on application by Edmonton Power, 1991 (Commissioning Schedule of Genesee Unit No.1)
Date
1991
Applicant
Edmonton Power
Application Number
910336
Hearing Panel
Evans RG
Mink, FJ
Prince JP
Hearing Type
Prehearing
Utilities
Category
Electric power
Descriptors
Electric power project
Genesee power plant
Benefit cost analysis
Capacity
Electric power demand
Electric power supply
Expansion
Forecasting
Planning
Power system interconnection
Notes
Memorandum of Decision on application no. 910336 by Edmonton Power respecting the commissioning schedule of the second unit of the Genesee Power Plant, Genesee 1; instead of prescribing a date by which the unit should be made available to the AIS, the ERCB should allow EP to determine, based on monitoring load growth on the air, when the unit should be completed; Prehearing meeting held 1991-05-22; Dated 1991-06-05
Interveners
City of Edmonton
Tadman, D
Pettican, A
Shinyei, F
TransAlta Utilities Corporation (TAU)
Dalgleish, T
Tapics, J
Way, D
Alberta Power Limited (APL)
Romanow, M
Laing, B
City of Calgary
Goss, R
Hanslip, G
Industrial Power Consumers Association of Alberta (IPCAA)
Crowther, D
Fording Coal Limited
Thrasher, R
Brander, R
Popowich, J
Shyluk, D
Northern Alberta and N.W.T. (Districh of Mackenzie) Building and Construction Trasdes Council and Alberta and Northwest Territories (District of Mackenzie) Building and Construction Trades Council (The Building Trades Councils)
Hall, M
Arsene, W
County of Leduc No. 25
Sjolie, B
CANA Limited
Launer, M
Less detail

Decision Memorandum of Decision 2001-08-17

https://had.aer.ca/link/decision3478
Applicant
Epcor Generation Inc.
Epcor Power Development Corpoaration
Application Number
2001173
Title
Memorandum of Decision 2001-08-17: Prehearing meeting EPCOR Generation Inc. and EPCOR Power Development Corp. expansion of genesee power plant
Date
2001
Title
Memorandum of Decision 2001-08-17: Prehearing meeting EPCOR Generation Inc. and EPCOR Power Development Corp. expansion of genesee power plant
Date
2001
Applicant
Epcor Generation Inc.
Epcor Power Development Corpoaration
Application Number
2001173
Hearing Panel
McCrank MN
Lock RG
Miller GJ
Hearing Type
Prehearing
Utilities
Descriptors
Expansion
Genesee Power Plant
Interveners
Alberta Environment
Canadian Environmental Assessment Agency
Clean Energy Coalition
Department of Fisheries and Oceans
ENMAX Energy Corporation
ENMAX Power Corporation
Enron Canada Corporation
Environment Canada
Fording Coal
Kruger Group
Mewassin Community Action Group
Paul First Nation
TransAlta Corporation
Buss K
Davies DG
Gaspe D
Kruger D
Secord RC
Stepaniuk DW
Vincent M
Wood DA
Yanor-McRae R
Less detail