Decision 75-10
https://had.aer.ca/link/decision2169
- Applicant
- City of Edmonton
- Edmonton Power
- Application Number
- 8149
- Title
- Decision on application by City of Edmonton, 1975 (Lambton substation and 240 KV transmission line)
- Date
- 1975
- Title
- Decision on application by City of Edmonton, 1975 (Lambton substation and 240 KV transmission line)
- Date
- 1975
- Applicant
- City of Edmonton
- Edmonton Power
- Application Number
- 8149
- Hearing Panel
- Millard V
- Berkowitz N
- Goodman CJ
- Hearing Type
- Board
- Utilities
- Category
- Transmission line
- Descriptors
- Edmonton area
- Electric substation
- Transmission line
- Electric power demand
- Environmental impact
- Locating
- NTS 83H
- Route selection
- Legal References
- Hydro and Electric Energy Act S9
- Hydro and Electric Energy Act S10
- Hydro and Electric Energy Act S11
- Hydro and Electric Energy Act S14
- Notes
- Decision 75-10 on application No. 8149 to construct and operate a double-circuit 240-KV transmission line and substation to supply the southeast Edmonton area.
- Interveners
- Beckwith Farms (1966) Ltd.
- Capital Management Ltd.
- Ross, D.K.
- Ross, Mrs. D.K.
- Calgary Power