50 records – page 1 of 3.

Decision 75-07

https://had.aer.ca/link/decision2172
Applicant
Calgary Power Ltd.
Application Number
7869
7823
7913
Title
Decision on application by Calgary Power Ltd., 1975 (transmission and substation facilities stony plain - Devon project)
Date
1975
Title
Decision on application by Calgary Power Ltd., 1975 (transmission and substation facilities stony plain - Devon project)
Date
1975
Applicant
Calgary Power Ltd.
Application Number
7869
7823
7913
Hearing Panel
Millard V
Strong JI
DeSorcy GJ
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Edmonton area
Electric substation
Stony Plain area
Transmission line
Environmental impact
Locating
NTS 83H
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S17
Notes
Decision 75-7 on application No. 7869, No. 7823 and to upgrade existing transmission and substation facilities in the area between Stony Plain and Devon, west of Edmonton.
Interveners
Goertz, R.
Halton-Grove REalty
Gray, D.S.K.
Estate of Elizabeth Bauer
Baron, H.
Weitzel, W.
Edmonton Regional Planning Council
Sigma Lands
Owners-Section 14-51-26-W4
Kapty, A.
Berretti, M
County of Parkland No. 31
McLean, W.
McLean, M.
QCTV
Devon Nurseries
Less detail

Decision 75-10

https://had.aer.ca/link/decision2169
Applicant
City of Edmonton
Edmonton Power
Application Number
8149
Title
Decision on application by City of Edmonton, 1975 (Lambton substation and 240 KV transmission line)
Date
1975
Title
Decision on application by City of Edmonton, 1975 (Lambton substation and 240 KV transmission line)
Date
1975
Applicant
City of Edmonton
Edmonton Power
Application Number
8149
Hearing Panel
Millard V
Berkowitz N
Goodman CJ
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Edmonton area
Electric substation
Transmission line
Electric power demand
Environmental impact
Locating
NTS 83H
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S10
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Notes
Decision 75-10 on application No. 8149 to construct and operate a double-circuit 240-KV transmission line and substation to supply the southeast Edmonton area.
Interveners
Beckwith Farms (1966) Ltd.
Capital Management Ltd.
Ross, D.K.
Ross, Mrs. D.K.
Calgary Power
Less detail

Decision 75-11

https://had.aer.ca/link/decision2168
Applicant
Calgary Power Ltd.
Application Number
8224
Title
Decision on application by Calgary Power Ltd., 1975 (construction and modification of transmission lines and substations near Lake Wabamun)
Date
1975
Title
Decision on application by Calgary Power Ltd., 1975 (construction and modification of transmission lines and substations near Lake Wabamun)
Date
1975
Applicant
Calgary Power Ltd.
Application Number
8224
Hearing Panel
Millard V
Berkowitz N
DeSorcy GJ
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Electric substation
Lake Wabamun
Transmission line
Electric power demand
NTS 83G
Route selection
Sundance power plant
Wabamun power plant
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S17
Notes
Decision 75-11 on application No. 8224 to construct and modify transmission line and substation facilities in the vicinity of the Sundance and Wabamun power plants.
Interveners
Henkel, N.
Less detail

Decision 76-13

https://had.aer.ca/link/decision2151
Applicant
Edmonton Power
Application Number
9188
Title
Decision on application by Edmonton Power, 1976 (transmission line of 240 KV and Jasper Substation)
Date
1976
Title
Decision on application by Edmonton Power, 1976 (transmission line of 240 KV and Jasper Substation)
Date
1976
Applicant
Edmonton Power
Application Number
9188
Hearing Panel
Millard V
Berkowitz N
DeSorcy GJ
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Edmonton area
Electric substation
Transmission line
Electric power demand
Environmental impact
NTS 83H
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S10
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Notes
Decision 76-13 on application No. 9188 to construct and operate a 240/72-KV substation and a 240 KV double circuit transmission line to serve the west Edmonton area.
Interveners
Calgary Power Ltd.
Famous Players Limited
Triple Five Corporation and Northern Trading Co. Ltd.
A Group of Eight Parties
Triple Five Corporation and a Group of Thirteen Parties
Less detail

Decision 77-12

https://had.aer.ca/link/decision2136
Applicant
Alberta Power Limited
Application Number
770171
Title
Decision on application by Alberta Power Ltd., 1977 (144 kv transmission line from Lloydminster to Metiskow)
Date
1977
Title
Decision on application by Alberta Power Ltd., 1977 (144 kv transmission line from Lloydminster to Metiskow)
Date
1977
Applicant
Alberta Power Limited
Application Number
770171
Hearing Panel
Craig DR
DeSorcy GJ
Goodman CJ
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Electric substation
Lloydminster area
Transmission line
Electric power demand
Electric power supply
Forecasting
NTS 73D
NTS 73E
Reliability
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S10
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Notes
Decision 77-12 on application No. 770171 to construct and operate a 144 KV transmission line from the Battle River north to Lloydminster (TP.45-50, R.1-2, W4M) and to connect the line to the Calgary power system and for a substation at Lloydminster; see also Decision 77-17 for other portion of line from Battle River to Metiskow
Interveners
Calgary Power Ltd.
Ranger, C.A.
Less detail

Decision 80-05

https://had.aer.ca/link/decision2034
Applicant
Calgary Power Ltd.
Application Number
790504
Title
Decision on application by Calgary Power Ltd., 1980 (240 KV transmission line in the Entwhistle-Whitecourt area)
Date
1980
Title
Decision on application by Calgary Power Ltd., 1980 (240 KV transmission line in the Entwhistle-Whitecourt area)
Date
1980
Applicant
Calgary Power Ltd.
Application Number
790504
Hearing Panel
Berkowitz N
Goodman CJ
Warne GA
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Electric substation
Transmission line
Whitecourt area
Agricultural land
Electric power demand
Environmental impact
Locating
NTS 83G
NTS 83J
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S10
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S14
Notes
Decision 80-5 on application No. 790504 for permits to construct and licences to operate a 240 KV transmission line designated as CP 919L from point near Entwhistle to Whitecourt (TP.53-59, R.6-12, W5M); Board hearing 1980-02-05/06 see also related Decision 78-17
Interveners
Alberta Power Limited
Lenko, P.S.
Lenko, Mrs.
Shumborski, R.
Shumborski, Mrs.
Farmers' Power Line Association et al Kurt Preugschas
Renlim Resources
Kobel, K.
Quinnell, G.D.
Town of Whitecourt
Miller, R.E.
Berget, J.L.
Berget. Mrs.
Less detail

Decision 80-22

https://had.aer.ca/link/decision2017
Applicant
Energy Resources Conservation Board
Application Number
800369
Title
Decision on application by Tebb (Mr. A.C. Tebb), 1980 (138 KV substation - Airdrie area)
Date
1980
Title
Decision on application by Tebb (Mr. A.C. Tebb), 1980 (138 KV substation - Airdrie area)
Date
1980
Applicant
Energy Resources Conservation Board
Application Number
800369
Hearing Panel
DeSorcy GJ
Bohme VE
Bray JA
Hearing Type
Board
Utilities
Category
Electric power
Descriptors
Airdrie area
Electric substation
Relocation
Land value
Locating
Urban development
Legal References
Hydro and Electric Energy Act S13
Notes
Decision 80-22 on application No. 800369 by Mr. A.C. Tebb to relocate the Calgary power Ltd. east Airdrie substation CP 199S from its presently approved location in section 14-27-29 W4M to either of 2 locations in the east Airdrie industrial park; Board hearing 1980-09-03/04
Interveners
Tebb, A.C.
Calgary Power Ltd.
G.I.C. Industries Ltd.
Woodland Properties Ltd.
Burnco Industries Ltd.
Don Beddoes Construction ltd.
Comanche Drilling Ltd.
Hamilton, H.A.
Less detail

Decision 80-A

https://had.aer.ca/link/decision2328
Applicant
Calgary Power Ltd.
Application Number
780363
780589
Title
Decision on application by Calgary Power Ltd., 1980 500 KV transmission lines, Keephills - Ellerslie
Date
1980
Title
Decision on application by Calgary Power Ltd., 1980 500 KV transmission lines, Keephills - Ellerslie
Date
1980
Applicant
Calgary Power Ltd.
Application Number
780363
780589
Hearing Type
Utilities
Category
Transmission line
Descriptors
Edmonton area
Electric substation
Ellerslie area
High voltage
Lake Wabamun
Transmission line
Biological effect
Electric field
Electric power
Demand (economics)
Health
Locating
NTS 83G
NTS 83H
Route selection
Safety
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S17
Notes
ERCB report 80-A on application No. 780363 and No. 780589 for permits to construct and operate two 500 KV transmission lines between Keephills generating station in Wabamun Lake area and proposed Ellerslie substation south of Edmonton (TP.50-52, R.23 W4M to R.5 W5M); Board hearing 1979-02-06 thru 1979-03-14 see also ERCB report 81-D for supplement to this Decision
Less detail

Decision 81-10

https://had.aer.ca/link/decision1757
Applicant
Calgary Power Ltd.
Application Number
810159
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line east Airdrie - Turbo)
Date
1981
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line east Airdrie - Turbo)
Date
1981
Applicant
Calgary Power Ltd.
Application Number
810159
Hearing Panel
Bray JA
Fox EG
Remmer WG
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Airdrie area
Electric substation
Transmission line
Electric power demand
Gas processing plant
Land value
NTS 82P
Oil refinery
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S15
Notes
ERCB Examiners report No. E81-10 on application No. 810159 to construct and operate a 138 KV line (No. CP 752L) from east Airdrie substation (No. CP 199S) to proposed Turbo substation (No. CP 391S) (TP.25-27, R.28-29, W4M).
Interveners
Town of Airdrie
Matlock, J.E.
Comanche Drilling Ltd.
Turbo Resources Limited
Goerlitz, A.
DeWaal, H.
Tebb, C.
Armada Builders Ltd.
Qualico Developments
Less detail

Decision 81-11

https://had.aer.ca/link/decision1756
Applicant
Calgary Power Ltd.
Application Number
800503
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line Vauxhall - Taber)
Date
1981
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line Vauxhall - Taber)
Date
1981
Applicant
Calgary Power Ltd.
Application Number
800503
Hearing Panel
Bellows LA
Homeniuk TF
Miller KF
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Brooks area
Electric substation
Taber area
Transmission line
Electric power demand
Environmental impact
Health
Locating
NTS 82H
NTS 82I
Route selection
Safety
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S17
Notes
ERCB Examiners report no.E81-11 on application No. 800503 to construct and operate a 138 KV transmission line between west Brooks substation CP 28S and Taber substation CP 83S and for approvals for Vauxhall substation CP158S (TP.10-13, R.16 W4M).
Interveners
Poynton, R.L.
214807 Holdings Ltd.
Rivers Cattle Ltd.
Town of Vauxhall
Less detail

Decision 81-13

https://had.aer.ca/link/decision1754
Applicant
Calgary Power Ltd.
Application Number
810089
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line Janet-Strathmore and 138/25 KV Strathmore substation)
Date
1981
Title
Examiners report on application by Calgary Power Ltd., 1981 (138 KV transmission line Janet-Strathmore and 138/25 KV Strathmore substation)
Date
1981
Applicant
Calgary Power Ltd.
Application Number
810089
Hearing Panel
Homeniuk TF
Dilay JD
Miller KF
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Strathmore area
Transmission line
Electric power demand
Locating
NTS 82I
NTS 82P
Reliability
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S15
Notes
ERCB Examiners report no.E81-13 on application No. 810089 to construct and operate a 138 KV transmission line CP 765L from existing Janet substation CP74S to proposed 138/25 KV substation CP 151S adjacent to Town of Strathmore (TP.23-24, R.25-28, W4M).
Interveners
McClain, D.M.
McClain, N.
Donair Limited
Knight, J.
5K Cattle Co. Ltd.
Less detail

Decision 81-17

https://had.aer.ca/link/decision1751
Applicant
Alberta Power Limited
Application Number
800961
Title
Examiners report on application by Alberta Power Ltd., 1981 (144 KV transmission line AP 285L Sheerness - Bullpound - Wintering Hills phase 2 Michichi Creek)
Date
1981
Title
Examiners report on application by Alberta Power Ltd., 1981 (144 KV transmission line AP 285L Sheerness - Bullpound - Wintering Hills phase 2 Michichi Creek)
Date
1981
Applicant
Alberta Power Limited
Application Number
800961
Hearing Panel
Mink FJ
Antonio HA
Wilson JF
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Drumheller area
Electric substation
Transmission line
Agricultural land
Irrigation
Locating
NTS 72M
NTS 82P
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S14
Notes
ERCB Examiners report no.E81-17 on application No. 800961 to construct and operate a 144 KV transmission connecting the Sheerness power plant to the Bullpound and Wintering Hills substations, and connecting Wintering Hills substation to existing 144 KV line AP 285L, and connecting north end of existing line AP 285L to proposed substation in Michichi Creek area (TP.25-29, R.13-20, W4M).
Interveners
Sundance Oil Canada Limited
The Ranchers
Russell, C.
Less detail

Decision 81-33

https://had.aer.ca/link/decision1734
Applicant
TransAlta Utilities Corporation
Application Number
810586
Title
Examiners report on application by TransAlta Utilities Corporation, 1981 (138 KV substation and transmission line Bruderheim area)
Date
1981
Title
Examiners report on application by TransAlta Utilities Corporation, 1981 (138 KV substation and transmission line Bruderheim area)
Date
1981
Applicant
TransAlta Utilities Corporation
Application Number
810586
Hearing Panel
Homeniuk TF
Dilay JD
Morin EJ
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Bruderheim area
Electric substation
Fort Saskatchewan area
Transmission line
Electric power demand
Environmental impact
Land use
Locating
NTS 83H
Oil refinery
Route selection
Legal References
Hydro and Electric Energy Act S9
Hydro and Electric Energy Act S11
Hydro and Electric Energy Act S13
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S15
Notes
ERCB Examiners report no.E81-33 on application No. 810586 to construct and operate a 138 KV transmission line from a point on existing transmission line (CP 706L) to a proposed 138/25 KV substation to be located east of the Town of Bruderheim (TP.55-56, R.20-221, W4M).
Interveners
Prokopczak, L.
Roloff, R.
Roloff, M.
Laird, B.
Hennig, D.
Maschmeyer, D.
Lukawesky, O.
Paul, D.
Paul, M.
Paul, A.
Less detail

Decision 82-01

https://had.aer.ca/link/decision1087
Applicant
TransAlta Utilities Corporation
Application Number
810705
Title
Examiners report on application by TransAlta Utilities Corporation, 1982, (240 KV double circuit transmission line, Entwistle to Edson and Bickerdike substation)
Date
1982
Title
Examiners report on application by TransAlta Utilities Corporation, 1982, (240 KV double circuit transmission line, Entwistle to Edson and Bickerdike substation)
Date
1982
Applicant
TransAlta Utilities Corporation
Application Number
810705
Hearing Panel
Homeniuk TF
Antonio HA
Moloney JK
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Edson area
Electric substation
Hinton area
Transmission line
Electric power demand
Locating
NTS 83F
NTS 83G
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S18
Notes
Examiners report E82-01 on application No. 810705 to construct & operate a 240 KV double circuit transmission line from section 20-52-7 W5M south of Entwhistle to a proposed substation near Edson.
Interveners
Dionne, C.L.
Tufty, R.A.
Quarrie, N.
Schaning, H.B.
Leteta, A.
Less detail

Decision 82-07

https://had.aer.ca/link/decision1139
Applicant
TransAlta Utilities Corporation
Application Number
810776
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138/69-KV transmission line 578L and Redwater substation 171S)
Date
1982
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138/69-KV transmission line 578L and Redwater substation 171S)
Date
1982
Applicant
TransAlta Utilities Corporation
Application Number
810776
Hearing Panel
Paterson RG
Yu JNG
Remmer WG
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Redwater area
Transmission line
Capacity
Electric power demand
Expansion
NTS 83H
Reliability
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S20
Notes
ERCB Examiners report E82-7 on application No. 810776 to construct and operate 1.6 km of 138-KV transmission line to be designated as 578L from the existing Redwater substation 171S to the existing transmission line 78L in the NE quarter of section 18-57-21 W4M.
Interveners
Lasner Construction Co. Ltd.
Less detail

Decision 82-08

https://had.aer.ca/link/decision1138
Applicant
TransAlta Utilities Corporation
Application Number
811025
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line CP 172AL Taber-Conrad)
Date
1982
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line CP 172AL Taber-Conrad)
Date
1982
Applicant
TransAlta Utilities Corporation
Application Number
811025
Hearing Panel
Bellows LA
Yu JNG
Mazurek LA
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Conrad area
Electric substation
Taber area
Transmission line
Electric power demand
Environmental impact
Locating
NTS 82H
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S18
Notes
ERCB Examiners report E82-8 on application No. 811025 to construct and operate a 138-KV transmission, CP 172AL, from existing transmission line CP 172L to proposed Conrad substation (TP.6-10, R.15-16, W4M).
Interveners
Shaw, B.R.
Leahy, G.
Less detail

Decision 82-14

https://had.aer.ca/link/decision2064
Applicant
Alberta Power Limited
TransAlta Utilities Corporation
Application Number
810608
810733
Title
Decision on application by Alberta Power Ltd. and Transalta Utilities Corporation, 1982 (240 kv transmission line facilities in the Louise Creek - Sagitawah area)
Date
1982
Title
Decision on application by Alberta Power Ltd. and Transalta Utilities Corporation, 1982 (240 kv transmission line facilities in the Louise Creek - Sagitawah area)
Date
1982
Applicant
Alberta Power Limited
TransAlta Utilities Corporation
Application Number
810608
810733
Hearing Panel
Goodman CJ
Morin EJ
Brushett ER
Hearing Type
Board
Utilities
Category
Transmission line
Descriptors
Electric substation
Swan Hills area
Transmission line
Electric power demand
Environmental impact
Land use
NTS 83J
Right of way
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Notes
Decision 82-14 on application No. 810608 by Alberta Power to construct & operate a 240-KV double circuit transmission line AP938L/939L to connect with Alberta Power's line at service area boundary and run south to existing Sagitawah substation CP 77S (TP.59-65, R.10-12, W5M).
Interveners
TransAlta Utilities Corporation
Esso Resources Limited
Federated Pipelines
Less detail

Decision 82-17

https://had.aer.ca/link/decision1131
Applicant
TransAlta Utilities Corporation
Application Number
820437
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV substation and transmission line Prentiss-Joffre area)
Date
1982
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV substation and transmission line Prentiss-Joffre area)
Date
1982
Applicant
TransAlta Utilities Corporation
Application Number
820437
Hearing Panel
Homeniuk TF
Fox EG
Remmer WG
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Prentiss area
Transmission line
Chemical plant
Electric power demand
Land use
Locating
NTS 83A
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S18
Notes
ERCB Examiners report E82-17 on application No. 820437 to construct and operate a double circuit 138-KV transmission line from a point on existing transmission line No. CP 756L near the Alberta gas ethylene plant near Joffre to proposed substation at the Union Carbide plant (TP.38-39, R.25-26, W4M).
Interveners
Union Carbide Canada Limited
Superior Sod Farm Ltd.
Less detail

Decision 82-19

https://had.aer.ca/link/decision1129
Applicant
TransAlta Utilities Corporation
Application Number
820378
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line WETASKIWIN-Pigeon Lake)
Date
1982
Title
Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line WETASKIWIN-Pigeon Lake)
Date
1982
Applicant
TransAlta Utilities Corporation
Application Number
820378
Hearing Panel
Antonio HA
Berndtsson NG
Wilson JF
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Pigeon Lake area
Transmission line
Wetaskiwin area
Bonnie Glen field
Electric power demand
Environmental impact
Gas processing plant
NTS 83A
NTS 83H
Route selection
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S18
Notes
ERCB Examiners report E82-19 on application No. 820378 to construct and operate a 138-KV transmission line from existing line 80L to existing Pigeon Lake substation (TP.46-47, R.24-28, W4M).
Interveners
Jaburek, H.V.
Hartwig, G.
Less detail

Decision 82-20

https://had.aer.ca/link/decision1128
Applicant
Alberta Power Limited
Application Number
820247
Title
Examiners report on application by Alberta Power Ltd., 1982 (144-KV transmission line Clairemont Lake-Friedenstal)
Date
1982
Title
Examiners report on application by Alberta Power Ltd., 1982 (144-KV transmission line Clairemont Lake-Friedenstal)
Date
1982
Applicant
Alberta Power Limited
Application Number
820247
Hearing Panel
Pow JR
Yu JNG
Allman RJ
Hearing Type
Examiners
Utilities
Category
Transmission line
Descriptors
Electric substation
Grande Prairie area
Transmission line
Electric power demand
Environmental impact
Failure
Locating
Noise (sound)
NTS 83M
NTS 84D
Reliability
Route selection
Site survey
Legal References
Hydro and Electric Energy Act S12
Hydro and Electric Energy Act S14
Hydro and Electric Energy Act S16
Hydro and Electric Energy Act S17
Hydro and Electric Energy Act S20
Notes
ERCB Examiners report E82-20 on application No. 820247 to construct & operate a substation at Clairmont Lake near Grande Prairie and 144-KV transmission line from proposed substation at Fairview, and an addition to existing Rycroft substation (TP.72-82, R.1-5, W6M).
Interveners
Woronuk, D.
The Village of Rycroft
Municipal District of Spirit River
Less detail