Decision 74-L
https://had.aer.ca/link/decision2452
- Applicant
- Calgary Power Ltd.
- Application Number
- 7165
- 7300
- Title
- Decision on application by Calgary Power Ltd., 1974 (respecting a transmission line through the Crowsnest Pass and an order for its connection to the electric system of the British Columbia Hydro and Power Authority)
- Date
- 1974
- Title
- Decision on application by Calgary Power Ltd., 1974 (respecting a transmission line through the Crowsnest Pass and an order for its connection to the electric system of the British Columbia Hydro and Power Authority)
- Date
- 1974
- Applicant
- Calgary Power Ltd.
- Application Number
- 7165
- 7300
- Hearing Panel
- Millard V
- Strong JI
- Berkowitz N
- Hearing Type
- Board
- Utilities
- Category
- Transmission line
- Legal References
- Hydro and Electric Energy Act S14
- Hydro and Electric Energy Act S9
- Hydro and Electric Energy Act S11
- Notes
- ERCB report 74-L on application No. 7165 to augment and develop existing interconnection of its power plants and transmission lines to B.C. Hydro system and application No. 7300 to construct and operate a 240 KV transmission line from Peigan substation through Crowsnest Pass to the Alberta-B.C. border and associated modifications to the substation; Board hearing 1973-12-11; rescheduled to 1973-12-18; postponed to 1974-01-21/22; permit and licence No. CP 74-13 and Order No. Misc HE 7408