Application 1016780
https://had.aer.ca/link/application39753
- Applicant
- Summit Resources Limited
- Summary
- Requesting approval to amend SU 2194 changing the drilling spacing units in sections 8 and 17-79-7W5, and amend the Mirage Halfway B unit DSU's to a 200 metre interwell distance with a 100 metre buffer zone, having one well per Lsd.
- Decision/Order/Approval
- SU 2194A
- Date Registered
- Dec. 17, 1997
- Applicant
- Summit Resources Limited
- Summary
- Requesting approval to amend SU 2194 changing the drilling spacing units in sections 8 and 17-79-7W5, and amend the Mirage Halfway B unit DSU's to a 200 metre interwell distance with a 100 metre buffer zone, having one well per Lsd.
- Category
- Reservoir Development
- Descriptors
- Spacing units
- Holding
- Amendment
- Drilling spacing units
- Area
- Mirage
- Date Registered
- Dec. 17, 1997
- Decision/Order/Approval
- SU 2194A