Decision 72-D-HE
https://had.aer.ca/link/decision2484
- Applicant
- City of Edmonton
- Title
- Decision on application by City of Edmonton, 1972 (for approval of the construction and operation of an addition to the Clover Bar power plant and for an order for its interconnection)
- Date
- 1972
- Title
- Decision on application by City of Edmonton, 1972 (for approval of the construction and operation of an addition to the Clover Bar power plant and for an order for its interconnection)
- Date
- 1972
- Applicant
- City of Edmonton
- Hearing Panel
- Govier GW
- Millard V
- Strong JI
- Berkowitz N
- Hearing Type
- Board
- Utilities
- Category
- Electric power
- Legal References
- Hydro and Electric Energy Act S7
- Notes
- ERCB report 72-D-HE on application by the City of Edmonton for approval of the addition of two 165 MW electric generating units to its Clover BAR power plant.