Decision 82-E
https://had.aer.ca/link/decision2314
- Applicant
- Shell Canada Resources Limited
- Application Number
- 810148
- 810149
- 810150
- 810663
- 810714
- 810715
- 810716
- Title
- Decision on application by Shell Canada Resources Limited, 1982 Shell proposed Moose and Whiskey Pipelines and related facilities, Kananaskis area
- Date
- 1982
- Title
- Decision on application by Shell Canada Resources Limited, 1982 Shell proposed Moose and Whiskey Pipelines and related facilities, Kananaskis area
- Date
- 1982
- Applicant
- Shell Canada Resources Limited
- Application Number
- 810148
- 810149
- 810150
- 810663
- 810714
- 810715
- 810716
- Hearing Panel
- Millard V
- Strom NA
- Evans RG
- Hearing Type
- Board
- Category
- Pipelines
- Descriptors
- Battery
- Compressor station
- Fuel gas pipeline
- Gathering line
- Gas pipeline
- Kananaskis Area
- Moose field
- Pipeline construction permit
- Sour gas
- Water disposal
- Water pipeline
- Whiskey field
- Atmospheric diffusion
- Conflict
- Disposal well
- Economic analysis
- Energy development
- Environmental impact
- ID-81-03
- IL-80-24
- Gas producing
- Hydrogen sulphide
- Land reclamation
- Land use
- NTS 82J
- NTS 82O
- Pipeline crossing
- Pipeline design
- Pipeline leak
- Pipeline route
- Recreational facility
- Safety
- Sulphur recovery
- Waste disposal
- Waste water
- Legal References
- Oil and Gas Conservation Act S26
- Pipeline Act
- Notes
- ERCB Reort 82-E on application no. 810148 for a pipeline to transport sweet fuel gas from Quirk Creek Plant to proposed Whiskey and Moose compressor stations; on application no. 810149 for pipeline to to transport sour gas from proposed compressor to Quirk Creek plant; on application no. 810150 for pipeline to transport sour gas from wellheads to proposed Moose and Whiskey compressor stations; on application no. 810663 for a pipeline to transport sour water from proposed compressor station to an injection well; on application no. 810714 to construct a gas battery with dehydration and liquid separation facilities and one compressor (LSD 4-35-21-5, W5M); on application no. 810715 to construct gas battery with dehydration and liquid separation facilities and two compressors (LSD 13-22-22-6, W5); and on application no. 810716 to dispose of sour water produced from Moose and Whiskey fields by injection into Mississippian Turner Valley Fm; Board hearing 1982-01-06/07/08/09/10/13/14/15 & 1982-02-01; See related ERCB Decisions 82-3, 82-12 and Report 82-D; See also ERCB Decision D83-22 on later Shell application (No. 830603) for Board to reconsider decision contained in this report