Decision 81-28
https://had.aer.ca/link/decision1738
- Applicant
- Alberta Power Limited
- Application Number
- 810135
- Title
- Examiners report on application by Alberta Power Ltd., 1981 (Bonnyville - Ethel Lake 144 KV transmission lines)
- Date
- 1981
- Title
- Examiners report on application by Alberta Power Ltd., 1981 (Bonnyville - Ethel Lake 144 KV transmission lines)
- Date
- 1981
- Applicant
- Alberta Power Limited
- Application Number
- 810135
- Hearing Panel
- Homeniuk TF
- Remmer WG
- Wilson JF
- Hearing Type
- Examiners
- Utilities
- Category
- Transmission line
- Descriptors
- Bonnyville area
- Transmission line
- Electric power demand
- Environmental impact
- Land use
- NTS 73L
- Route selection
- Legal References
- Hydro and Electric Energy Act S9
- Hydro and Electric Energy Act S11
- Hydro and Electric Energy Act S13
- Hydro and Electric Energy Act S14
- Hydro and Electric Energy Act S17
- Notes
- ERCB Examiners report no.E81-28 on application No. 810135 to construct and operate a single circuit 144 KV transmission line from Bonnyville substation (AP 700S) to Ethel Lake substation (AP 717S) and double circuit 144 KV line from Ethel Lake substation to Ethel junction (TP.61-64, R.2-6, W4M).
- Interveners
- Shandro, S.
- Kunec, M.
- Kunec, B.
- Lakeland Environmental Agricultural Protection Society
- Kunec, J.