Decision 82-19
https://had.aer.ca/link/decision1129
- Applicant
- TransAlta Utilities Corporation
- Application Number
- 820378
- Title
- Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line WETASKIWIN-Pigeon Lake)
- Date
- 1982
- Title
- Examiners report on application by TransAlta Utilities Corporation, 1982 (138-KV transmission line WETASKIWIN-Pigeon Lake)
- Date
- 1982
- Applicant
- TransAlta Utilities Corporation
- Application Number
- 820378
- Hearing Panel
- Antonio HA
- Berndtsson NG
- Wilson JF
- Hearing Type
- Examiners
- Utilities
- Category
- Transmission line
- Descriptors
- Electric substation
- Pigeon Lake area
- Transmission line
- Wetaskiwin area
- Bonnie Glen field
- Electric power demand
- Environmental impact
- Gas processing plant
- NTS 83A
- NTS 83H
- Route selection
- Legal References
- Hydro and Electric Energy Act S12
- Hydro and Electric Energy Act S14
- Hydro and Electric Energy Act S16
- Hydro and Electric Energy Act S17
- Hydro and Electric Energy Act S18
- Notes
- ERCB Examiners report E82-19 on application No. 820378 to construct and operate a 138-KV transmission line from existing line 80L to existing Pigeon Lake substation (TP.46-47, R.24-28, W4M).
- Interveners
- Jaburek, H.V.